hydrostroy

We Build Building and Great Homes.

We successfully cope with tasks of varying complexity, provide long-term guarantees and regularly master new technologies.

Get in touch

(+380) 50 318 47 07

65 Allerton Street 901 N Pitt Str, Suite 170, VA 22314, USA

The project includes a complete reconstruction of a wastewater treatment plant (WWTP) in the city of “Golden Sands”, modernization of existing facilities, and expansion. The station is designed for a load of 72,122 residents and guests during the summer months and 18,000 during the winter period. Construction began in 2017. The first stage, providing for the strengthening of the existing pilot structure No. 1, has been completed, and a permit for use has been issued since 2019. The construction and installation works for the reconstruction, modernization, and expansion of the treatment plant in the second stage have been completed.

INVESTOR: VARNA MUNICIPALITY