The implementation of the facility is within the framework of the project “Construction of a wastewater treatment plant – Tryavna and a collector leading to it” worth BGN 13.1 million.
The project was financed under the Operational Program “Environment 2007-2013” (OPES).
Design and construction of a new WWTP, including supply and installation of technological equipment, personnel training, and commissioning, were carried out. A flow collector and flow technical infrastructure have been built.
COMPLETION DATE: May 2015
INVESTOR: TRYAVNA MUNICIPALITY